FDD - Floating Dry Dock 

fdd1.jpg 2.jpg4.jpg3.jpg

Floating Dry Dock

FDDs or Floating Dry Docks are easier to operate and can take up to ships of sizes Panmax and above. There will be a wharf, Finger pier for after docking repairs so that another ship can be taken for Dry Dock repairs.

Depending on the size of ships, FDD sizes also vary. The water front length and other facilities also vary. The ideal size will be to take ships of 120 metres length. The area of land required is 12.13 Hectares (30 Acres) with a water front of 100 metres. The land should be of roughly square in shape. Undredged draft of sea should be at least 6 metres. It can be dredged and increased to 11 metres.

Investment (calculated in January 2020) - Cost of FDD + Infrastructure  USD 24 Million (excluding the cost of land).

 Time of completion 4 years.